Paris Ave from Central to the west will be replaced with a new concrete road beginning November 9, 2023 in anticipation of the completion of Beck’s.

Project timeline will be as follows to plan for an alternate route:

SCHEDULE AND TIMING AS FOLLOWS:

North Side of Roadway Shut Down

November 9, 2023 - Sawcut Of North Side And Removal Start

November 10, 2023 - Removal Of Pavement On North Side Of Roadway

November 13, 2023 - Base Prep Of North Side Of Roadway

November 14, 2023 - Pavement Pour North Side Of Roadway

South Side of Roadway Shut Down

November 20, 2023 - South Side Of Roadway Shut Down Open North Side Of Roadway

November 21, 2023 - Removal Of Pavement On South Side

November 22, 2023 - Removal And Prep Of South Side Of Roadway

November 23, 2023 - Prep Of South Side Of Roadway

November 24 - November 26, 2023
Thanksgiving Holiday

November 27 -November 29, 2023 - Roadway Pour South Side

December 4, 2023 - South Side Road Open